Redmoor Academy
The Brief
Modern kitchen transformation at Redmoor Academy to serve 1,400 pupils
Midlands Catering Projects were appointed to complete a full design and build at Redmoor Academy in Hinckley. The project involved stripping out the existing 1980s-style canteen and delivering a modern, efficient kitchen within a tight six-week programme during the summer holidays.
The client required a space that could reliably cater for up to 1,400 pupils, with durable, high-performing equipment to improve operational efficiency.
What we did
Complete kitchen installation with prep, storage, and wash-up facilities
We sourced, supplied, and installed several key components to create a fully functional kitchen facility, including:
- Staff changing and toilet areas
- Dry and chilled storage areas
- Cold room
- Food preparation areas
- Cookline
- Chef’s pass
- Dedicated wash-up area
How we did it
Seamless kitchen design, build, and installation delivered on time
Drawing on our full range of expertise, we delivered a complete turnkey solution, including:
- Kitchen design
- Equipment supply
- Mechanical and electrical installation
- Ventilation systems
- CDM management
- Full strip-out of existing canteen
- Safety flooring
- PVC wall cladding
- New ceiling grid installation
Careful planning and coordination ensured we remained on track to meet the summer holiday deadline.
The RESULTS
Successful kitchen overhaul to meet the demands of 1,400 students
We successfully completed the project within the six-week timeframe, handing over a fully updated, operational kitchen ready for the new school year. The space is now equipped to meet the demands of 1,400 students and features robust, reliable equipment that supports improved kitchen performance and efficiency.